Emergency work to repair and replace the storm-ravaged seawall and coastal path at Snells Beach is due to begin this week, Auckland Council says.
The work will be carried out in two phases – firstly, construction of the seawall and reinstatement of the reserve land, which is expected to be finished by December 22, weather permitting.
The second phase will be replacing the footpath, which is scheduled to start on January 8 and should be finished by the end of the month, again, if weather permits.
The footpath will be closed parallel to the length of Sunburst Avenue while work is carried out, but the boat ramp will remain open.