Work will start soon on a $1.5 million upgrade of a Silverdale wastewater pipeline, a year after Te Herenga Waka o Ōrewa Marae raised concerns with Watercare over repeated sewage overflows into the Te Weiti/Wade River.
Watercare will replace around 170m of ageing wastewater rising main connected to the Blue Gum Pump Station, near Blue Gum Avenue. Construction is expected to start shortly, with the new pipeline due to be operating by the end of February next year.
Watercare says the new section of pipe will significantly reduce the risk of future overflows, improving environmental outcomes and providing a more reliable wastewater service for the growing community.
The project follows a series of failures last year, which resulted in wastewater entering the river. Kereama Nathan, from Te Herenga Waka o Ōrewa Marae, told the Watercare board, that the marae had experienced longstanding issues associated with the nearby pump station, including odour, and that the situation had worsened following four wastewater overflows during the year.
The marae asked Watercare to develop a plan to prevent further discharges into the river.
Alongside the infrastructure upgrade, Restore Hibiscus and Bays, Whitebait Connection and the marae will plant native trees and shrubs along the river.
Watercare project manager Ronald Gunda said Watercare recognised the importance of the Te Weiti/Wade River to mana whenua and mātāwaka, and was committed to protecting the mauri of the awa while delivering essential upgrades to ensure the wastewater network continued to serve the growing community safely and reliably.
“The works will be undertaken with careful consideration for the surrounding environment, minimising disruption to the reserve by utilising a trenchless construction method.
“The new section of pipe will be installed using horizontal directional drilling, which allows the pipe to be installed via series of shafts, rather than excavating a continuous trench through the reserve.”