Matakana Link Road October 2022

Work continues on the Te Honohono to Kai – Matakana Link road pavement, with 70% of footpaths completed, kerb is 90% complete, cycleways are being constructed and the foundation pad for two rest areas and two bus stops have been poured.

Wetlands and rain gardens are all planted and all utilities underneath the bridge are installed except the watermain.

A total of 73 streetlights have been installed and 16 are live on Matakana Road.

Wharehine and Auckland Transport have shared the following flyover: 

Visit the Auckland Transport page here for more information https://at.govt.nz/projects-roadworks/te-honohono-ki-tai-matakana-link-road/matakana-link-road-project-update-october-2022/