Overhaul for island wharves

Two wharves on Kawau Island are getting a major overhaul to the tune of nearly $6 million this year, courtesy of Auckland Transport (AT).

School House Wharf, on the southern side of the island’s main Bon Accord Harbour, is first in line, with a partial rebuild due to start in early April. The work will include the replacement of hardwood decking, wharf head piles, fender sleeves, bracing and wrapping of existing piles.   

AT said the total cost for School House Wharf was approximately $1.3 million, with completion planned for the end of June, subject to weather conditions.

In May, South Cove Wharf is set for a comprehensive rebuild, following site investigations and pile assessments in October last year.

An AT spokesperson said the full remedial solution would involve the strategic replacement of piles, bracing, joists, bearers and decking, using more robust and longer-life hardwood materials and steel piles. Seawall repairs will also be carried out at the wharf.    

“The total project cost is approximately $4.5 million, subject to confirmation of construction methodology,” they said. 

“Construction will take approximately four to six months, as the site is exposed and works are heavily weather dependent. In a worst-case scenario, construction will be completed in early November.”

Old sheds at both wharves were also due to be removed and replaced.      

“We will be renewing the wharves on Kawau Island to ensure they remain operational for both locals and tourists,” the spokesperson added.

“There might be some noise, but we’ll try to minimise it. Normal ferry services should continue without disruption – we’ll plan the construction to minimise public access impact, though some sections of the wharf will need to be closed at times.

“We’re working closely with the community to keep everyone informed throughout this project.”