Pipe gets go ahead after re-routing and delays

The new pipe will run between the new pumping station currently under construction at Lucy Moore Memorial Park and Snells Beach.

Watercare has been given the green light to start digging a 5km pipeline from Warkworth to Snells Beach this spring, following the granting of resource consent by independent commissioners and no subsequent appeals against it.

The pipe will run from the new pump station being built in Lucy Moore Memorial Park, under the Mahurangi River and south west to the new Snells-Algies Wastewater Treatment Plant.

Watercare chief infrastructure officer Steve Webster said the pipeline was the critical connecting piece in a $300 million-plus regional investment programme, though its re-routing, coupled with Covid and consent issues, meant that the overall finish date had been pushed back from this year to 2025.

Watercare was forced to go back to the drawing board for the pipeline in 2019, after plans for an 8.5km pipe, part of which was to run along Sandspit Road, were met with fierce local opposition.

“We sought feedback from the community, including the Rodney Local Board, and the result was loud and clear: digging up Sandspit Road – an already very busy road – was not acceptable,” Webster said.

“The revised design cuts out 3.5km of pipe and eliminates the need for two pump stations, which reduces the carbon footprint from both construction and the operation of these assets, and brings down the project cost.

“By using trenchless tunnelling technology instead of open trenching in the road reserve, we’ll also be greatly reducing any traffic disruption.”

Moving construction off roads and into tunnelling also reduced health and safety risks for contractors, he added.

The tunnelling will be carried out in stages. The first section will start from 584 Hamilton Road and head back to Warkworth, and the second will be from the Snells Beach treatment plant back to 99 Hamilton Road, with the last tunnelling drive connecting the two sections of Hamilton Road. 

“When this work is complete, the pipe will carry Warkworth’s wastewater to the treatment plant, where it will be treated to a very high quality before it’s discharged at the new ocean outfall we completed in 2020,” Webster said.

“This programme of work will help to clean up the Mahurangi River, by removing the current treated wastewater discharge into the river from the existing Warkworth wastewater treatment plant, and reduce overflows in the network.

“It also enables development in the Warkworth area, which is expected to swell to 28,000 people by 2050.”

However, uncertainty surrounds whether the new treatment plant will be online and operating before housing developments north of Warkworth need connecting, with existing plants already at near capacity.

Another new pipeline, to transfer wastewater from those new developments to the Lucy Moore pumping station, is still under consideration.

Watercare said four options were being looked at and, once landowner approval and consents had been obtained, construction was expected to start next year.