State Highway 1 and Ara Weiti Road
Night closures will take place on State Highway 1 (SH1) from Sunday, August 10 to Thursday, August 14. During the closure, the SH1 overbridge will have its barriers ‘stitched’ into place as they are concreted to the bridge deck, while stormwater pipes are installed underneath.Earthworks and pavement construction continue around Ara Weiti Road and East Coast Road.
Stillwater
Tower crane construction is underway on the Weiti River Bridge site as the bridge ‘super structure’ build commences, which the team says is a significant milestone for the project. The first concrete pours on Pier 4 and the river pylons on the eastern side of the river, also begin, along with the future Duck Creek Road interchange construction as Auckland Transport has completed the widening works around ‘turkey bend’.
Whangaparāoa
Earthworks commenced for the new Whangaparāoa Road alignment on the eastern corner of Whangaparāoa and Cedar Terrace. The future realigned intersection at Beverley Road will also have road surface, kerb and channel and footpath construction from mid-August. Drainage installation next to Whangaparāoa Road will continue at night.